Spain sets 80 per cent renewable power rule for data centres
The government has also approved water-efficiency standards, reporting duties and restrictions on where sensitive data can be held.

Spain’s Council of Ministers has approved a Royal Decree requiring data centres to demonstrate that renewable sources supply 80 per cent of the electricity they consume. The government aims to bring the sector’s expansion into line with grid capacity and Spain’s environmental commitments.
Operators must match renewable generation with consumption on an hourly basis and meet additionality criteria intended to encourage new clean electricity production. The rules provide for long-term electricity contracts, self-consumption and storage.
A voluntary transitional arrangement will allow operators to accept priority disconnection when needed to protect grid stability. Projects already undergoing approval will generally be given six months to meet the new conditions.
The decree also sets interim restrictions on electricity and water consumption while European criteria are being finalised. Larger facilities will face sustainability reporting duties, alongside requirements incorporating European transparency and efficiency rules into Spanish law.
For information systems classed in high categories under the National Security Framework, the most sensitive data must stay within the European Economic Area. Access from third countries for administration, maintenance and support will face tighter controls. Breaching certain obligations could trigger financial compensation requirements and sanctions, including the suspension of grid connection and access rights for as long as three years.
Sara Aagesen, Third Vice-President and Minister for Ecological Transition, said data centres had been granted 15 gigawatts (GW) of grid access capacity, with another 20 GW awaiting approval.